Perimeter Wall Painting Project

  • 3 days ago
  • 1 min read

April 10th Update




We have finished patching, now onto painting!

 

Despite the rainy weather, the painters were able to prime most of the exterior of the Promenade wall. Next week, they will complete priming on the interior side before beginning painting later in the week.

 

Once Promenade is complete, work will continue along the opposite wall on Masters Blvd, followed by Bella Citta Blvd, Goodman Rd, and Legends Blvd.



 
 