Gate Project Update:

  • admin
  • Oct 4, 2025
  • 1 min read
  • Phase 4 Gates Operational by October 13th

  • Links/Legends Work Begins October 7th



Work is moving along smoothly at the Mandalay (Phase 4) gates. All new conduit and exit loops are expected to be completed by Monday, 10/6, with installation of the new barrier arms and operators beginning Tuesday, 10/7. The gates will remain open during this phase and are expected to be fully operational by Monday, 10/13.

 

Next up, Links/Legends Gate! Work will begin on Tuesday, 10/7. Starting Thursday, 10/9, gates will be open and traffic patterns will be adjusted while crews work on each side of the gate. Please drive carefully, traffic will be routed through the exit gate while the entrance is under construction, and vice versa.


Thank you for your continued patience and cooperation as we keep the project moving forward!


Gate Project Schedule as of 10/3 (subject to change as the work progresses)



 
 